Building Europe's Data Centres at Speed and Scale

EnergyHeadhunter.de/News / Conference Notes

Data Centres & Construction

Building Europe's Data Centres at Speed and Scale

Most new European data centre space is leased before it is finished, so every week counts. Developers, contractors, a scheduler and an insurer explained how the best teams win time back.

Night view of Europe from space with network connections

DICE Europe 2026 · From Ground to Grid: Delivering European Data Centres at Speed and Scale

Space pre-leased in major hubs (JLL)

~75%

Cut by re-sequencing one programme

60 days

Switch room build, modular

20 → 10 weeks

Single insurance programmes

$4.5bn+

Key takeaways

  • Europe can build more, but not the old way: permits, power, communities and skills are all constraints at once.
  • One playbook doesn't travel: consistent outcomes for customers need local people, local partners and local codes.
  • Speed now comes from the factory and the schedule: modular kits and smarter planning are saving weeks, not days.
  • Handover starts on day one: with most capacity pre-leased, a missed ready-for-service date is the biggest risk.

The second round table moved from capital to concrete: how to actually deliver Europe's next wave of data centres. On stage were Tony Jacob (QTS), Amy Daniell (STACK EMEA), John Hawkins (IBM), Brigitte Perera (ALICE Technologies), Christopher Jelfs (Laing O'Rourke) and Simon Simpson (Aon), with John Delargy of Procore in the chair. Data centres, he noted, used to operate quietly in the background, like invisible industrial plumbing. Today they make front-page headlines.

Can Europe Triple Its Capacity?

Brussels wants to triple EU data centre capacity within five to seven years. The panel split on whether that is possible.

Can Europe triple data centre capacity in 5–7 years? Yes, but differently John Hawkins, IBM • Engage communities from day one • Better coordination on power • Work closely with local government • Industrialise how we build (Jelfs) No, not without the EU A developer on the panel • Permitting has closed Milan • Problems in Norway, Finland, Denmark • Power, press and communities against us • Needs collaboration across the EU
Source: From Ground to Grid round table, DICE Europe, 12 Nov 2026

“The answer is yes, we will get there. But we're going to have to do some things differently.”

John Hawkins, Global Cloud Data Center Real Estate Lead, IBM

The sceptic's case was blunt: core markets where data centres once went up easily have become extremely difficult, and the UK's recent data centre covenant drew sharp criticism from the stage. Hawkins agreed the mood has shifted almost overnight. He pointed to a recent Financial Times report suggesting some communities would now rather host a nuclear plant than a data centre, and to the US local votes that mostly went against the industry. He still believes Europe will get there. The two agreed to put a date in the diary and look back in a few years.

Laing O'Rourke's Christopher Jelfs offered the most practical answer: open the industry up. Data centre projects used to rely only on people with data centre experience. Now they are drawing in talent from other systems-heavy sectors such as power, nuclear and healthcare, and borrowing their methods, above all designing for manufacture and assembly.

One Playbook Doesn't Travel

What works in Frankfurt will not work in Madrid or Milan. For QTS's Tony Jacob, the first priority is still consistency: customers want the same technical and schedule outcomes everywhere, with no surprises. But he has seen many businesses, particularly from the US, try to impose one way of working on Europe, and it always backfires. In Frankfurt, he noted, local people know you don't build in steel.

“You can't just delegate or dump it out to a supply chain and say, get on with it. You have to be in amongst it.”

Tony Jacob, SVP Development – Europe, QTS Data Centers

His answer is local knowledge, local culture, local codes, local partners and local language speakers, with active owners who stay involved through pre-development and pre-construction. It cannot be run centrally from Europe or globally: it needs boots on the ground.

Permitting shows why. Asked which country is easiest, STACK's Amy Daniell surprised the room with Switzerland: onerous, but completely transparent. The cantons tell you exactly what they need, so her team hit every requirement and received permits six months early. Milan is the opposite example.

Clear rules beat easy rules Switzerland Onerous, but fully transparent Every requirement known upfront Permits arrived 6 months early Catch: power and few contractors Milan New study requested mid-process ≈6 weeks of extra modelling Then 45 more days of consultation Officials wary of public scrutiny
Source: Amy Daniell (STACK EMEA) and Tony Jacob (QTS), DICE Europe, 12 Nov 2026

“It's onerous, but at least you know where you stand.”

Amy Daniell, SVP Strategy and Development, STACK EMEA, on Swiss permitting

In Milan, authorities came back asking for a study of the combined impact of nearby data centres: six weeks of modelling, then another round of public consultation. The work itself would have been no drama, Daniell said, if it had been asked for at the start. Jacob added that officials everywhere are now extra cautious because of public scrutiny, and that more jurisdictions are trying to change the rules for projects already in the queue. Whether an application is grandfathered under the old rules has become a live question.

Speed Comes From the Factory and the Schedule

Most schedules are now factory-dependent: the critical items are long-lead equipment, not site work. Building off-site doesn't remove complexity, the panel agreed, but it moves it into a controlled environment.

Where the time is being saved Examples given on stage Switch room, conventional 20 wks Switch room, modular 10 wks Re-sequencing, same crews 60 days saved 30-day supply delay recovery plan in 24 hours
Source: Christopher Jelfs (Laing O'Rourke) and Brigitte Perera (ALICE Technologies), DICE Europe, 12 Nov 2026
  • Design for manufacture from the outset: deploying a kit of parts, as power, nuclear and healthcare do, can dramatically increase capacity, but only if it is decided at the start, not as a procurement choice later (Christopher Jelfs, Laing O'Rourke).
  • Test your habits: schedules carry a lot of “preferential logic”, such as building east to west because the last project did. One North American team re-sequenced its pre-construction plan with the same crews and cut 60 days (Brigitte Perera, ALICE Technologies).
  • Replan in hours, not weeks: a hyperscale owner hit by a 30-day procurement delay had recovery options on the table within 24 hours, using overtime rather than extra crews (Perera).
  • Build a buffer: QTS's US business can store product in factories and call it off for projects. Europe lacks that luxury, so Jacob is codifying products that can be easily modified per market, with more off-site testing and commissioning, and audits across multiple factories.
  • Check your insurance: off-site manufacturing reduces site losses, but transport becomes a risk and off-site defects may not be covered by the main programme. Make sure delay-in-startup and defect cover respond (Simon Simpson, Aon).

“If you're only planning your schedule up front, you're printing directions before a road trip. It works until you hit traffic.”

Brigitte Perera, Manager, Customer Success, ALICE Technologies

The tools still need skilled people behind them, the panel added: someone on site who sees that productivity was only 50% today and updates the plan. A shared “golden schedule”, a standard template refined for each site's permits, access, water and power, is where many teams are heading.

Handover Starts on Day One

The stakes are high: JLL estimates nearly three-quarters of the space under construction in major hubs is already leased, and panellists believed the real figure in top markets is close to 100%. Tenants watch every milestone.

“Handover has got to start from day one.”

Christopher Jelfs, Data Centres Sector Lead, Laing O'Rourke

Jelfs wants commissioning plans known early so programmes are built around assets rather than zones, watertight interfaces between owner-supplied vendors, equipment makers and the general contractor, and every quality issue closed before commissioning starts. A developer on the panel described sitting down with contractors in Milan, then a new market, to walk them through a ready-for-service checklist they had never seen. Simple, but it worked.

Jacob compared the market to air traffic control: many planes loaded and ready, but only so many slots. His advice to colleagues was not to be over-ambitious on ready-for-service dates, because power on time, temporary power and construction power are all pre-start conditions. Some in the market, he warned, sign commitments they know they cannot meet and accept the penalties. Most serious clients won't accept that, and neither will QTS.

Designing for Densities Nobody Can Predict

For years the industry stabilised around classic cloud deployments. GPUs and very high densities have broken that. Masterplans now have to allow for low, medium and high density, and high-density layouts can leave a lot of wasted space.

Three ways to design for unknown densities Build for everything Maximum flexibility “Comes at an enormous cost” Double down on high density Needs early customer signals Different building form factor Kit of parts Standard components, bespoke models Learn from the car industry The panel's preferred route
Source: Tony Jacob (QTS) and Christopher Jelfs (Laing O'Rourke), DICE Europe, 12 Nov 2026

“Flexibility comes at an enormous cost. We simply can't afford, as an industry, to build buildings so flexible that they meet the highest common denominator.”

Tony Jacob, SVP Development – Europe, QTS Data Centers

Power backup is changing too. Some countries are pushing battery systems instead of diesel, but moving a customer from 48 hours of fuel to two to four hours of battery takes real confidence in the grid, given renewable instability and cyber threats. And AI's spiky power profile will demand new UPS solutions, so standardisation must not become dumbing down.

The hardest part to keep flexible is the permit. The panel's tactic is to permit the largest, tallest, worst-case version of a building, then, if a high-density customer arrives, shrink it and give the spare land back to the community, for example as gardens. Never re-permit, Daniell warned: that is a disaster. And requirements vary hugely, from 10–15 pages in some places to 400 certified documents in others.

Do the Numbers Still Stack Up?

“There wouldn't be the amount of money coming into this market if returns weren't still there.”

Amy Daniell, SVP Strategy and Development, STACK EMEA

Higher costs are being passed on through higher lease rates and build-to-suit deals with agreed costs. Daniell sees plenty of upside for those who are smarter: cheaper land sourced by local people, distressed industrial assets, and a better relationship with the grid operator, including selling capacity back during maintenance windows. Lease rates have roughly doubled in a couple of years, another panellist said, and customers now ask whether you have capacity before they ask about price.

Jacob's lesson came from the pandemic: leases signed before construction contracts were bought out were hit by double-digit inflation, and yields fell fast. QTS now scrutinises every line of the business case, capital costs, penalties and operating costs, to protect the return once it is set.

Insurance is the hidden constraint. Aon's Simon Simpson said the global market's capacity for a single construction programme used to be 3.5 to 4.5 billion. Aon is now placing programmes bigger than that, and as campuses grow and GPUs go in, values keep climbing. Developers are even asking to insure the penalty risk of missing ready-for-service dates when permitting rules change mid-build.

What CEOs and project leaders should take away

  1. Design for manufacture on day one: modular only pays off if it shapes the design, not just procurement.
  2. Put people on the ground: consistent outcomes need local partners, local codes and active owners.
  3. Choose markets with clear rules: predictable permits are worth more than easy ones.
  4. Promise honest ready-for-service dates: power, not construction, usually decides them.
  5. Check your insurance early: off-site defects, transport and delay risk need explicit cover.

Next in this series: what the “Power First” round table said about securing electricity for Europe's next data centres.

This article reflects what EnergyHeadhunter.de understood from the “From Ground to Grid” round table at DICE Europe 2026, based on our own notes. Figures and quotes reflect our notes and understanding of the discussion.

ExecWisA

Where CEOs share views and inspire each other. Coffee Mornings, CEO Private Tables and our Annual Meeting — by application, for CEOs of medium and large enterprises.

How we meet →

Join the conversation

Have a view your peers should hear?

We interview CEOs and senior leaders shaping business in Hungary and beyond. Tell us about the question you have already answered.

Contact usEnergyHeadhunter.de

POWERED BY

ExecutiveHeadhunter.com, international executive search

EnergyHeadhunter.de, driving the green transition