What Europe's Data Centre Boom Looks Like From the Top

Data Centres & Investment

We had the pleasure of attending the European Data Centre Investment Conference & Expo in London. Here are our notes from EnergyHeadhunter.de and ExecutiveHeadhunter.com.

Building 100 MW of data centre capacity now costs about $1.5bn, and a grid connection can take a decade. At DICE Europe, four leaders from investment, development and public affairs explained where the capital is going, what it fears, and why communities now help decide.

Notes from the opening round table “Capital, Confidence and Competition”, by Sándor Vizi, Partner, The Executive Headhunter Ltd.

7 min read · 16 Nov 2026 · News / Conference Notes · Part 1 of the DICE Europe series

DICE Europe 2026 · Bisnow

Capital, Confidence and Competition

Lord's Cricket Ground, London · 12 November 2026

Adam Eaton (CEO, VIRTUS Data Centres), James Colvin (VP, DigitalBridge), Allan Bosley (Director, Public Affairs, Ark Data Centres) and Michael Ortiz (CEO, Core Foundry Digital Infrastructure), moderated by Rob Donell (Partner, Eversheds Sutherland).

$1.5bn

to build 100 MW of data centre capacity

10 years

possible wait for a grid connection in FLAP-D hubs

10–12%

levered returns targeted on finished assets

73 GW

UK data centre queue, vs 43–45 GW national generation

Key takeaways

  • Power picks the map: land with power deliverable within two years is the scarcest asset in Europe, and capital is moving to wherever the grid has room.
  • Tier two is becoming tier one: Berlin, Milan, Barcelona and Brussels are winning projects that the traditional hubs can no longer host.
  • The money works, at a price: banks fund 75–80% of a project, but equity cheques are huge and the market for selling finished assets is only just forming.
  • Consent is now part of the business case: investors check zoning and community risk before they buy land.

The opening round table set the tone for the day. It brought together Adam Eaton (CEO, VIRTUS Data Centres), James Colvin (VP, DigitalBridge), Allan Bosley (Director, Public Affairs, Ark Data Centres) and Michael Ortiz (CEO, Core Foundry Digital Infrastructure), moderated by Rob Donell (Partner, Eversheds Sutherland). Between them they covered the four questions every investor in this sector is now asking.

Power Decides Where Europe Builds

Power strategy now takes up most of an investor's working day, according to DigitalBridge's James Colvin. Over the past 24 months, grids in Europe and North America have become even more constrained. In the FLAP-D hubs (Frankfurt, London, Amsterdam, Paris and Dublin), a good new connection can take up to a decade, which is pushing large AI workloads towards the Nordics and Iberia.

“If you hold powered land today with a 24-month delivery schedule, that really is gold dust. That's incredibly rare.”

James Colvin, VP, DigitalBridge

In the US, grid operators now ask developers for collateral to clear speculative projects out of the queue, and the same practice is expected to reach Europe. The conclusion: barriers to entry will keep rising for as long as demand stays this strong.

The UK shows what happens when policy runs ahead of the grid. In the view of Ark's Allan Bosley, the AI Growth Zones were launched without checking where power was actually available.

The UK's data centre queue is bigger than all its power generationGigawatts. The queue is 1.7x national generationData centre connection queue73 GWTotal UK generation~43–45 GW
Source: Allan Bosley, Ark Data Centres, DICE Europe, 12 Nov 2026

“You cannot have governments coming in to try to create markets when they don't fully understand them.”

Allan Bosley, Director, Public Affairs, Ark Data Centres

The mood has since changed and policy is better informed, Bosley believes, and VIRTUS's Adam Eaton pointed to progress on Ofgem's proposals for managing the connection queue. The US picture, from Core Foundry's Michael Ortiz: a grid that is around 70 years old in places, and new capacity that takes years and billions to add.

Tier Two Is the New Tier One

Capital is moving from crowded hubs to tier-two citiesTraditional hubs (FLAP-D)Where capital is goingFrankfurtvery expensive to buildLondon, Amsterdam, Paris, Dublinconnections can take up to 10 yearsBerlinVIRTUS: two campusesMilanVIRTUS: brownfield sites under constructionBarcelona, BrusselsArk: expanding beyond the UKNordics, Iberialarge AI workloads
Source: Adam Eaton (VIRTUS), James Colvin (DigitalBridge) and Allan Bosley (Ark), DICE Europe, 12 Nov 2026

VIRTUS had already moved away from the FLAP-D hubs before Adam Eaton arrived as CEO, and he is doubling down: two campuses in Berlin and sites under construction in Milan. Frankfurt has become very expensive to build in, so its demand is rolling over into Berlin. Italy, one of Europe's largest economies, was underdeveloped for data centres, and the departure of light industry around Milan has left plenty of brownfield land. The Italian government is currently supportive, and the next question is whether Eastern Europe opens up.

Ark is taking a similar path into Barcelona and Brussels, where local authorities want more capacity. As Bosley put it, borrowing his CEO's comparison: why go to the busiest, muddiest waterhole in the Serengeti when there is clean water nearby?

Two cautions came from the panel. Every market is different, and local partners who know the municipality, the grid and the community matter more than ever; in Switzerland, Colvin noted, nothing happens without a relationship with the local canton. And the industry follows demand rather than creating it.

“If there's no customer looking at those markets, then we won't be looking to build out in those markets.”

Adam Eaton, CEO, VIRTUS Data Centres

VIRTUS rarely enters a market first: it lets someone else lead, then follows close behind.

Follow the Money: How a Data Centre Gets Financed

The capital behind data centres has changed completely over two decades:

Early yearsPrivate equityshort enterprisecontractsHyperscaler eraInfrastructure fundslonger leases,stronger creditTodayReal estate capitaljoins: cheques areastronomicalExitPension andsovereign fundsbuy finished assets
Source: James Colvin, DigitalBridge, DICE Europe, 12 Nov 2026

Today 100 MW costs roughly $1.5bn to build. With a creditworthy tenant, lenders cover 75–80% of the cost, but the equity is still massive, and much of it comes from closed-ended infrastructure funds with limits on how much they can put into one asset.

100 MW costs about $1.5bn: even with 75% debt, equity is still hugeIndicative financing of one 100 MW data centre, $bnDebt, 75% of cost: $1.125bnEquity: $0.375bn
Source: James Colvin, DigitalBridge, DICE Europe, 12 Nov 2026 · illustrative split at 75% loan-to-cost

“The scale of the capital required in this industry is astronomical. Creative sources of capital are not an option anymore. They're vital.”

James Colvin, VP, DigitalBridge

The answer is recycling. Developers take the construction risk, then sell the finished building, with its long hyperscaler lease, to pension and sovereign wealth funds that want a steady income for 25 years. That market is young: only three or four deals were live at the time, and single sites with smaller equity cheques sell more easily in Europe. Few operating assets are ready to sell yet, Eaton added, because the industry was small ten years ago.

  • Returns: buyers target levered returns of about 10–12%, slightly above core infrastructure.
  • Why the premium: European sales still carry operational and service-level risk; the US model of triple-net “powered shells” has barely arrived.
  • Different buyers, different appetites: infrastructure funds accept operating risk, while many real estate investors only want triple-net leases where the tenant maintains everything.
  • Terminal value: depends on budgeting enough maintenance spending to refresh the electrical and mechanical plant over the asset's life.

“It is not wide, but it is widening.”

James Colvin, VP, DigitalBridge, on the pool of buyers for finished data centres

Building for a Customer Who Keeps Changing Its Mind

One hyperscale customer Michael Ortiz has worked with for 15 years changes its specification every six months. His comparison: a Bentley in grey is easy to sell; the same car five years later with an orange leather interior is not.

The developer builds the standard; the customer pays for the bespokeBespoke fit-oute.g. 300 kW racks, new room layoutCustomer pays, on its own balance sheetdemarcation lineAdaptable spinepower and cooling routes for any hyperscalerDeveloperPowered core and shellleased for 15–20 yearsDeveloper: financeable and resaleable
Source: Michael Ortiz, Core Foundry Digital Infrastructure, DICE Europe, 12 Nov 2026

The answer is a financeable core and shell with an adaptable “spine” that would suit Amazon, Google or Meta, leased for 15–20 years, with a clear line drawn above it. Anything bespoke beyond that line, such as 300 kW racks or a new room layout, is paid for on the customer's own balance sheet.

“The customer is always going to change their mind. When they start footing the bill, they're less prone to come back to you.”

Michael Ortiz, CEO, Core Foundry Digital Infrastructure

  • Energy contracts: in the US, every 100 MW of power purchase agreement means about $1.3bn of commitment. If a tenant takes 300 MW but the developer has signed for 600–900 MW, the exposure is too big for investors. “If you don't have that addressed, that conversation doesn't even happen.”
  • How hyperscalers deploy: in “triads” of 300 MW each, forming 900 MW clusters. Training models can sit anywhere, but inference has to sit close to people.
  • Copy-paste terms don't travel: investors often want one market's terms repeated in the next, but costs and delivery times can be radically different.

The Licence to Operate Is Now an Investment Criterion

“Each of you in this room has probably interacted with a data centre something like 3,000 times today, but you didn't know you were doing that.”

Allan Bosley, Director, Public Affairs, Ark Data Centres

For 30 years the industry hid behind anonymity. Customers demanded it: ten years ago they wanted no numbers or logos on the buildings. Projects ran like secret “skunkworks” with code names; today, public websites track every US project by county and permit. AI has made data centres visible, and feared.

The industry's own engagement scorecardAs rated on stage by Adam Eaton, CEO, VIRTUS Data CentresGovernmentSignificantly better than 2–3 years agoMainstream mediaGetting betterLocal communitiesQuite poor
Source: Adam Eaton, VIRTUS Data Centres, DICE Europe, 12 Nov 2026

Even a derelict brownfield site, once used for illegal raves, draws objections, Eaton admitted. Ortiz's checklist is “PCA”: planning, community and adaptability. He also warned against the industry's favourite argument.

“The biggest misnomer that you can lead into a conversation with the public is: well, we create jobs.”

Michael Ortiz, CEO, Core Foundry Digital Infrastructure

Few people work at a data centre itself; the real benefit is the ring of investment around it, much like the railway depots of the past: towns that took part prospered, and those that didn't withered.

For investors, the risk is now concrete. Unzoned land is a big red flag, permitting is stricter than ever, and DigitalBridge writes enforcement clauses into tenant contracts. Its portfolio companies now meet the groups campaigning against data centres to hear their concerns, and Colvin wants the industry to speak with one voice. Bosley pointed to a model that works: the Greater London Authority brought data centre operators, local councils, Energy UK, network operators and the Environment Agency around one table to plan growth together.

What CEOs and investors should take away

  1. Buy power, not land: check that a connection offer is mature, paid for and dated.
  2. Look beyond FLAP-D, but follow demand: tier-two cities win when a customer is already there.
  3. Separate the shell from the fit-out: keep bespoke changes on the tenant's balance sheet.
  4. Settle the energy contract early: who carries the power purchase agreement decides whether investors engage.
  5. Budget for community engagement from day one: it now affects zoning, permits and price.

Next in this series: what the “Power First” round table said about securing electricity for Europe's next data centres.

This article reflects what EnergyHeadhunter.de, the energy division of ExecutiveHeadhunter.com, understood from the opening round table at DICE Europe 2026, based on our own notes. Figures and quotes reflect our notes and understanding of the discussion.

ExecWisA

Where CEOs share views and inspire each other. Coffee Mornings, CEO Private Tables and our Annual Meeting — by application, for CEOs of medium and large enterprises.

How we meet →

More from ExecWisA

Energy & Finance

Big Projects, Patient Capital: What the EIB Can Do for Hungary's Energy Transition

In conversation with Stefania Ciraolo, Head of the EIB Group Office in Hungary.

7 min read · 25 Oct 2026

Energy

Build the Grid, Price It Fairly, Unlock Flexibility

E.ON Hungária's CEO says this year's price spikes, negative prices and near-brownout are symptoms of a system in transition.

5 min read · 3 Nov 2026

Join the conversation

Have a view your peers should hear?

We interview CEOs and senior leaders shaping business in Hungary and beyond. Tell us about the question you have already answered.

Contact usEnergyHeadhunter.de

POWERED BY

ExecutiveHeadhunter.com, international executive search

EnergyHeadhunter.de, driving the green transition